Covered Bridge Restoration and Relocation :: 3G Construction :: Holderness, NH

Covered Bridge Restoration and Relocation

Relocation of the Whittier Covered Bridge


2008 - Relocation of the Whittier Covered Bridge

  • Design and install major emergency stabilization of the deteriorated trusses
  • Whittier Covered Bridge built 1870
  • 144' Paddleford arch truss
  • Design and installed temporary shoring in the river and rolled bridge onto dry land
  • Owner: The town of Ossipee, N.H.
  • Engineer: Hoyle Tanner & Associates
  • Contact: Sean James

Mouse over an image for an enlarged view or click here for a slideshow